Earned Value Analysis

Venkataramiah S Annapragada
24/12/2018 0 0

It Compares Performance Measurement Baseline to the actual schedule and cost performance. Performance Measurement Baseline integrates Scope Baseline, Schedule Baseline and Cost Baseline.

 

For each work package the following dimensions are calculated :

  • Planned Value [PV]. Work that was planned to have been completed at a given point of time
  • Budget At Completion [BAC]. Total planned value for the project. Also called Cost Baseline
  • Earned Value [EV]. The measure of work performed at a given point of time
  • Actual Cost [AC]. The total cost incurred to complete the work measured in EV

 Percentage Project Complete at a given point of time. Percentage of EV/BAC

0 Dislike
Follow 2

Please Enter a comment

Submit

Other Lessons for You

What is M.S.Project ?
MICROSOFT PROJECT contains project work and project groups, schedules and finances.Microsoft Project permits its users to line realistic goals for project groups and customers by making schedules, distributing...

PMP Certification Exam For Project Management Professionals
There are several prospective employment opportunities for a project management professional. As a result, many applicants take a jab at the PMP certification exam. PMP preparation then becomes more and...

PMP - Exam & It's Importance
PMI'S PMP is globally recognized as one of the challenging certifications that needs lot of skills, hard work, and years of experience for sitting in the examination. Once you get PMP tag with your name,...

PMP(Project Management Professional)
PMP is the hottest career options for professionals in project management field. It provides project managers with certification that is helpful in their career. PMP is the most reputed certification...
S

Sprintzeal

0 0
0

Learning is Planning and then achieving.
Self-learning is the best learning. Reading the content twice or thrice makes an individual cover about 40% of the chapter and is subject to the grasping power and the prior interest as well. Make...
X

Looking for PMP Training Classes?

The best tutors for PMP Training Classes are on UrbanPro

  • Select the best Tutor
  • Book & Attend a Free Demo
  • Pay and start Learning

Learn PMP Training with the Best Tutors

The best Tutors for PMP Training Classes are on UrbanPro

This website uses cookies

We use cookies to improve user experience. Choose what cookies you allow us to use. You can read more about our Cookie Policy in our Privacy Policy

Accept All
Decline All

UrbanPro.com is India's largest network of most trusted tutors and institutes. Over 55 lakh students rely on UrbanPro.com, to fulfill their learning requirements across 1,000+ categories. Using UrbanPro.com, parents, and students can compare multiple Tutors and Institutes and choose the one that best suits their requirements. More than 7.5 lakh verified Tutors and Institutes are helping millions of students every day and growing their tutoring business on UrbanPro.com. Whether you are looking for a tutor to learn mathematics, a German language trainer to brush up your German language skills or an institute to upgrade your IT skills, we have got the best selection of Tutors and Training Institutes for you. Read more